Fire House Construction Update

untitled-4749

The day after Christmas 2015 and all through the house … – is on schedule.

The roof framework over the house is almost complete, the apparatus bay walls and roof framework is on-going and on schedule. The building is really starting to take shape now. Soon we will see some enclosure and work will pick-up inside.

 

Firehouse Construction December 10th

untitled-4690

December 10th, the carpenters are three days into their work. The outside walls for the first floor are up, the position of the interior walls are laid out and reviewed. Site work is ongoing and progressing as scheduled. The roof deck over the apparatus bays can be seen in the background. This is the front corner of the building and the side wall facing west.